Environmental assessment activities

The project has implemented the following activities as part of the required environmental assessment process:

Environmental assessment activities Year
LNG export license received from National Energy Board (NEB) Dec. 16, 2013
Project Description submittal to BC EAO and CEAA Dec. 31, 2014
Section 10 Order received from BC EAO Jan. 7, 2015
Substitution decision received from CEAA Feb. 26, 2015
Section 11 Order received from BC EAO April 27, 2015
Draft Application Information Requirements (dAIR) submittal to BC EAO May 8, 2015
Valued Component Selection Document submittal to BC EAO May 8, 2015
Initial Working Group meeting June 23, 2015
Public Consultation Plan submittal to the BC EAO June 26, 2015
Aboriginal Consultation Plan submittal to the BC EAO Oct 30, 2015
BC EAO Public Comment Period on dAIR Nov. 23, 2015 to Jan. 6, 2016
BC EAO-hosted open house Dec. 8, 2015
Final AIR approved by BC EAO Mar. 31, 2016
Public Consultation Report submittal to the BC EAO April 1, 2016
Aboriginal Consultation Report submittal to the BC EAO April 13, 2016
Export license extension from 25 year to 40 years granted by NEB July 28, 2016
Section 13 Order received from BC EAO Aug. 30, 2016